Which power factor correction solution fits your load?
The load decides the technology. A bank that suits steady motors can fail early on a plant full of drives.
| Your load | Usual choice |
|---|---|
| Steady, low harmonics | Contactor-switched bank without reactors |
| Steady, with drives, UPS or rectifiers | Bank with detuned reactors |
| Changes every few cycles: welding, cranes, lifts, presses | Thyristor-switched bank or static var generator |
| Capacitive or leading power factor | Static var generator |
| Harmonics above your limits | Harmonic filters |
| Medium voltage motors or substations | MV capacitor banks and MV capacitors |
Choose 60 Hz equipment for Saudi Arabia
Saudi Arabia’s public grid runs at 60 Hz. Many capacitor ranges are made in separate 50 Hz and 60 Hz versions, and their kvar ratings are not interchangeable. Check the frequency in the product name before ordering, or ask us to confirm it.
Not sure what you need? Our power factor correction service starts with a measurement. See also how SEC power factor penalties work.
Frequently asked questions
What frequency should I order for Saudi Arabia?
Saudi Arabia’s public grid runs at 60 Hz. Order the 60 Hz version of a capacitor bank or capacitor unless your site has its own 50 Hz supply.
Do I need detuned reactors?
Usually yes if drives, UPS or rectifiers are a significant part of the load. Reactors stop the capacitors from resonating with the network and amplifying harmonics. A harmonic measurement settles the question.
Can you size the bank for us?
Yes. Send recent electricity bills and the transformer rating, or let us measure the load. We size the kvar, the steps and the reactors, then quote the bank, installation and commissioning.
Know the part number? Power Factor Correction Product Codes
Request a quotation or datasheet
Tell us the model or the application. An engineer replies within one business day.
Call an engineer WhatsApp us